MEETING DATE: 2/18/2020
DEPARTMENT: RESOURCE MANAGEMENT AGENCY
DEPT HEAD/DIRECTOR: Harry Mavrogenes, Director of Resource Management Agency
AGENDA ITEM PREPARER: Damon Felice
SBC DEPT FILE NUMBER: 790
SUBJECT:
RESOURCE MANAGEMENT AGENCY – H. MAVROGENES
Approve Plans, Specifications and Bid Solicitation of the Homeless Services Center Phase III Bid Package - PWB-2001; and authorize the adverting for bids.
SBC FILE NUMBER: 790
AGENDA SECTION:
CONSENT AGENDA
BACKGROUND/SUMMARY:
On December 1, 2017 phase I of the new San Benito County Homeless Services Center opened to the public and phase II was completed on July 31, 2019. Phase III will added six (6) dormitory type facilities and all the associated services. The work will take place in the eastern most end of the existing facility. Bids will be due on March 18, 2020 and this project is scheduled to come back to the Board for consideration of contract award on April 7, 2020. Construction will take several months and be completed in September 2020.