Item Coversheet

SAN BENITO COUNTY

AGENDA ITEM
TRANSMITTAL FORM

Mark Medina

District No. 1

Anthony Botelho

District No. 2

Peter Hernandez

District No. 3

 

Jim Gillio

District No. 4
Vice-Chair

Jaime De La Cruz

District No. 5
Chair


Item Number: 9.



MEETING DATE:  2/4/2020

DEPARTMENT:
RESOURCE MANAGEMENT AGENCY

DEPT HEAD/DIRECTOR: Harry Mavrogenes, Director of Resource Management Agency

AGENDA ITEM PREPARER: Noel Suan

SBC DEPT FILE NUMBER: 105

SUBJECT:

RESOURCE MANAGEMENT AGENCY - H. MAVROGENES

Approve a contract with MNS Engineers, Inc., to provide construction contract administration, engineering, inspection, and materials testing services for the construction of the PWB-1911 Hospital Road Bridge - Low Water Crossing Replacement Project – FAP No. BRLKS-NBIL(501) in the amount not to exceed $1,498,880.02; Authorize the Chair, Board of Supervisors. to execute the Contract with MNS Engineers, Inc.

SBC FILE NUMBER: 105



AGENDA SECTION:

CONSENT AGENDA

BACKGROUND/SUMMARY:

The plans and specifications for the construction of the PWB-1911 Hospital Road Bridge - Low Water Crossing Replacement Project – FAP No. BRLKS-NBIL(501) was adopted by the Board on October 22, 2019.  The approved resolution included the authorization for advertising the project for construction upon the contract award for consultant services for construction contract administration, engineering, inspection, and materials testing on the project.  However, Caltrans has advised staff to award this project by late March of this year or sooner as they anticipate that available funding for high cost bridge projects such as this will start running out in May.  Should the project funding run out, federal reimbursements will likely be delayed until federal fiscal year 2021/2022.

As it is in the best interest of the County to avoid further delay on this project as well as to ensure federal reimbursement be available after the project is awarded, staff has deemed it necessary to advertise this project for construction on January 24, 2020 prior to board approval for the consultant services for construction contract administration, engineering, inspection, and materials testing on the project.  The bid opening is scheduled for February 27, 2020. 

MNS Engineers, Inc. is deemed to be the most qualified consultant to provide the requested services resulting from the Request for Proposal Process in compliance with the procedures in Chapter 10 of the Caltrans Local Assistance Procedures Manual (LAPM), entitled "Consultant Selection".   Staff has also received approval from Caltrans to proceed with the consultant contract award as required for federal aid reimbursement associated with the requested consultant services.

RMA will return to the board for award of the construction bid to the lowest responsible bidder on March 24, 2020. Construction is anticipated to begin in May/June 2020 and is expected to last until early 2022.

 

The project construction cost is estimated at $11,500,000.



BUDGETED:

Yes

SBC BUDGET LINE ITEM NUMBER:



CURRENT FY COST:



STAFF RECOMMENDATION:

It is recommended that the Board of Supervisors:

  1. Approve to contract with MNS Engineers, Inc., to provide the construction contract administration, engineering, inspection, and materials testing services for the construction of the PWB-1911 Hospital Road Bridge - Low Water Crossing Replacement Project – FAP No. BRLKS-NBIL(501).

  2. Authorize the Chair, Board of Supervisors to execute the Contract with MNS Engineers, Inc.



ADDITIONAL PERSONNEL:
No


BOARD ACTION RESULTS:

Approved contract per staff recommendation (5/0 vote). 
ATTACHMENTS:
DescriptionUpload DateType
Contract1/31/2020Standard Contract