MEETING DATE: 7/23/2019
DEPARTMENT: RESOURCE MANAGEMENT AGENCY
DEPT HEAD/DIRECTOR: Harry Mavrogenes
AGENDA ITEM PREPARER: Gregory J. Bucknell, PE
SBC DEPT FILE NUMBER: 105
SUBJECT:
RESOURCE MANAGEMENT AGENCY – H. MAVROGENES
Accept all bids for the Lovers Lane Road & Drainage Repairs 0.91 Miles N of Shore Drive PWD-1909, find Monterey Peninsula Engineering as the lowest responsive responsible bidder, award contract to Monterey Peninsula Engineering in the amount of $97,615.00, approve contract and authorize the RMA Director to execute the contract upon receipt of all contract documents required in the Invitation for Bids, and authorize the RMA Director to issue change orders in an amount of not to exceed $9,761.50 (10 % of Contract Amount).
SBC FILE NUMBER: 105
AGENDA SECTION:
CONSENT AGENDA
BACKGROUND/SUMMARY:
On May 21, 2019, the Board of Supervisors adopted the plans and specifications for the Lovers Lane Road & Drainage Repairs 0.91 Miles N of Shore Drive PWD-1909: find the project is categorically exempt under CEQA Guidelines Sections 15301 and 15302; and advertisement for bids.
Bids were due on June 27, 2019 at 3:00 PM and three bids were received. Staff has identified Monterey Peninsula Engineering as the lowest responsive responsible bidder in the amount of $97,615.00. The other bids received were from McKim Corporation in the amount of $117,842.63 and from Graniterock in the amount of $116,960.00. The Engineer’s Estimate was $139,340.00.
BUDGETED: