Item Number: 37.



MEETING DATE:  2/5/2019

DEPARTMENT:
COUNTY ADMINISTRATION OFFICE

DEPT HEAD/DIRECTOR: Ray Espinosa

AGENDA ITEM PREPARER: Stewart Patri

SBC DEPT FILE NUMBER: 120.5

SUBJECT:

COUNTY ADMINISTRATION OFFICE - R. ESPINOSA

Receive update on jail financing sources and approve Budget Adjustment  recommendation in the amount of $1,445,394.00. (4/5 vote)

SBC FILE NUMBER: 120.5



AGENDA SECTION:

REGULAR AGENDA

BACKGROUND/SUMMARY:

The County began construction on a jail expansion project in September of 2017. Housing for 72 beds, program space, medical area, intake/release functions, and administrative offices are included in the expansion project. Total cost of the project was estimated at $25,016,394. The outline of the Budget Summary is as follows:

 

Line Item State AB900 Cash Match In-Kind Match Total
Construction 13,000,000 8,146,844 21,146,844
Misc. Costs 625,000 90,000 715,000
Architect 1,428,000 136,510 1,564,510
Const. Manage. 954,040 954,040
CEQA 18,000 18,000
Audit 2,000 2,000
Site Acquisition 280,000 280,000
Needs Assessment 67,000 67,000
County Admin. 240,000 240,000
Transition Plan 19,000 19,000
Real Estate Due Dil. 10,000 10,000
Total Cost $15,053,000 $9,345,394 $618,000 $25,016,394

 

Financing Sources:

 

Multiple sources will be used for the funding of this project including state AB900/AB109 funding and financing. The following information outlines the adopted FY18/19 budgeted funding sources for the project:

 

  • AB900 (State aid): $13,000,000
  • Financing: $9,516,394
  • AB109: $2,500,000

 

Staff recommends a budget amendment to recognize the actual funding amount from AB900 as well as a decrease to the financing amount and an increase in General Fund Contribution to complete the project in FY18/19. The following table outlines the amendment:

 

Funding Source Subtotal Total Amount
AB900 - State Funding $15,053,000
Financing (COPs) $7,500,000
     General Fund 17/18 $400,000
     General Fund 18/19 $1,445,394
Total General Fund $1,845,394
In-Kind Match $618,000
Total $25,016,394

 

The County was approved for AB900 funding in the total amount of $15,053,000 for the project. In FY17/18 $400,000 was contributed from the General Fund to help cover the cost of construction management. In-kind match was also required for the project in the total amount of $618,000. An additional $9,000,000 in funding is required to complete the project.

 

Staff has prepared a financing structure for board approval of $7,500,000 of Certificates of Participation (COPs) and is recommending the use of general fund balance for the additional $1,445,394. Total general fund contribution by the end of the project will be approximately $1,900,000.

   

The additional general fund contribution is recommended for the following reasons:

 

  • Interest Savings over the life of the loan.
  • Encumbrance of only one leased asset, Sheriff/RMA building. The building is worth approximately $7.5 million. This will leave additional County assets available for the bonding of potential future projects.
  • Annual payments under $500,000.
  • General fund will be reimbursed through Detention Facilities Impact Fees as they become available.

 

COP's Repayment Structure:

 

The annual financing payment is estimated to be $482,564 over 30 years. Staff has recognized two funding sources that will cover this ongoing cost: Detention Facilities impact fees and an agreement between the County and Community Corrections Partnership Committee to provide $250,000 for 20 years. Detention facilities impact fees are estimated to generate $21,403,600 by 2035 for Jail and Juvenile Hall Expansion projects.

 

Funding from the two sources will cover the annual financing payment as well as reimburse the general fund contribution of $1,900,000.

 

 

 



BUDGETED:

No

SBC BUDGET LINE ITEM NUMBER:



CURRENT FY COST:



STAFF RECOMMENDATION:

1. Accept presentation from staff; and

2. Approve budget amendment for general fund transfer to the CIP Fund in the amount of $1,445,394 for the construction of the County Jail expansion project. (4/5 vote)



ADDITIONAL PERSONNEL:
No


BOARD ACTION RESULTS:

Approve per staff recommendation (5/0 vote). 
ATTACHMENTS:
DescriptionUpload DateType
Budget Adjustment1/31/2019Cover Memo