Item Coversheet

SAN BENITO COUNTY

AGENDA ITEM
TRANSMITTAL FORM

Mark Medina

District No. 1

Anthony Botelho

District No. 2

Chair

Peter Hernandez

District No. 3

 

Jim Gillio

District No. 4
Vice - Chair

Jaime De La Cruz

District No. 5

 


Item Number: 5.



MEETING DATE:  10/23/2018

DEPARTMENT:
COUNTY ADMINISTRATION OFFICE

DEPT HEAD/DIRECTOR: Ray Espinosa

AGENDA ITEM PREPARER: Dulce Alonso

SBC DEPT FILE NUMBER: 425

SUBJECT:

COUNTY ADMINISTRATION OFFICE - R. ESPINOSA

Delegate authority to CAO to finalize, approve and execute Change Order to Engie Energy Services contract in the amount up to $257,297.00, upon negotiation and available financing and subject to approval by County Counsel for legal content.

SBC FILE NUMBER: 425



AGENDA SECTION:

CONSENT AGENDA

BACKGROUND/SUMMARY:

On July 24, 2018 the Board of Supervisor approved a contract with Engie Services U.S for a project consists of the design, construction, installation, and monitoring of certain energy conservation measure improvements to various County facilities. 

 

Pursuant to the agreement, Engie Services U.S has performed pre-construction testing and investigations within the required time period. Furthermore, Engie Services U.S has timely submitted a change order request in the amount of one hundred twenty-five thousand dollars ($125,000) for the additional scope of work and requested to discuss the additional change order costs in the meet and confer process.  In accordance with Section 5.04 of the agreement, the change order increasing the contract amount shall not be binding on the County without specific approval from the Board of Supervisors.

 

The total market value of the proposed change order is $257,297.00.  Pursuant to the contract, the County would have the right to terminate the contract upon the payment of $50,000, or enter into a meet & confer process regarding the proposed change order.  Staff recommends that the County meet and confer regarding the additional change order amount, to determine whether to agree to equitable reductions to the scope of the project, or additional compensation.

 

FISCAL IMPACT

 

As mentioned in prior agenda items, using conservative assumptions, the project is forecasted to generate a savings of over $11 million over the life of the project.

 



BUDGETED:

Yes

SBC BUDGET LINE ITEM NUMBER:



CURRENT FY COST:



STAFF RECOMMENDATION:

Delegate authority to CAO to finalize, approve and execute Change Order to Engie Energy Services contract in the amount up to $257,297.00, upon negotiation and available financing and subject to approval by County Counsel for legal content.



ADDITIONAL PERSONNEL:
No


BOARD ACTION RESULTS:

Approved per staff recommendation (5/0 vote). 
ATTACHMENTS:
DescriptionUpload DateType
engie's proposed change order form10/19/2018Backup Material
Engie Change Order 110/18/2018Contract Amendment
Engie Contract 10/16/2018Cover Memo