MEETING DATE: 9/11/2018
DEPARTMENT: RESOURCE MANAGEMENT AGENCY
DEPT HEAD/DIRECTOR: John Guertin
AGENDA ITEM PREPARER: Adam Goldstone
SBC DEPT FILE NUMBER: 130
SUBJECT:
RESOURCE MANAGEMENT AGENCY - J. GUERTIN
Accept all bids received for the Homeless Services Center Building Improvements Phase II project, find Tombleson, Inc. as the lowest responsive responsible bidder, award contract to Tombleson, Inc. in the amount of $1,222,000.00, approve contract and authorize the RMA Director to execute it upon receipt of all documents required in the Invitation for Bids, and authorize the RMA Director to issue change orders per Public Contract Code 20142.
SBC FILE NUMBER: 130
AGENDA SECTION:
CONSENT AGENDA
BACKGROUND/SUMMARY:
When the Health and Human Services Agency first obtained grant funding for the creation of a Homeless Services Center and purchased the building at 1161 San Felipe Road in 2016, the plan was to create a comprehensive, multi-phase project. Phase I included the construction of a homeless shelter using a CDBG award and was completed in November 2017. Phase II design began shortly thereafter and includes staff offices, client training rooms, and kitchen and laundry facilities for the shelter. Phase III will begin design shortly and includes transitional housing.
This Phase II project was advertised for bids in July with bids due on August 16. Three bids were received and staff identified Tombleson Inc. as the lowest responsive, responsible bidder. Construction would begin in early October and be completed in April.
BUDGETED:
Yes
SBC BUDGET LINE ITEM NUMBER:
300.70.3500.1301.650.206
CURRENT FY COST:
STAFF RECOMMENDATION:
1. Accept all bids received for the Homeless Services Center Building Improvements Phase II project; and
2. Find Tombleson, Inc. as the lowest responsive responsible bidder; and
3. Award contract to Tombleson, Inc. in the amount of $1,222,000.00; and
4. Approve contract and authorize the RMA Director to execute it upon receipt of all documents required in the Invitation for Bids; and
5. Authorize the RMA Director to issue change orders per Public Contract Code 20142.
ADDITIONAL PERSONNEL: No