Approve contract with Don Chapin Company for the Slope Stabilization on Southside Road at Blossom Lane project, for the period of July 31, 2018 through December 31, 2018, not to exceed the amount of $397,458.00; approve budget augmentation in the amount of $397,458.00 from County contingencies; and authorize the RMA Director to approve change orders up to 10% of the contract amount.(4/5 vote)
SBC FILE NUMBER: 105
AGENDA SECTION:
REGULAR AGENDA
BACKGROUND/SUMMARY:
On June 12, 2018, the County entered into a contract with Don Chapin Co. to stabilize the hillside at the intersection of Southside Rd. and Blossom Rd. Unfortunately, after significant work had been completed on the initial hillside slide, the hill has had two additional slide occurrences necessitating substantial additional work. It is anticipated that this second contract will be sufficient to fully stabilize the hillside and make necessary repairs to the adjacent road and property. Combined, the two contracts total $1,057,458.
Below is a Rough Order schedule and estimated cost for the remaining work that is assumed on the Southside Slide Project. This is based only on the work that has been previously directed by staff, including the excavation and haul off of material in the "third" slide area, furnish and install jute netting and waddle in locations directed, furnish and install hydro-seeding on exposed areas, excavation and repaving of damaged areas marked by staff, and re-striping of Southside Rd.
The cost and schedule given does not assume any further slippage or take into account any unforeseen conditions. All work will continue to be performed on a Time & Materials basis as directed by staff and confirmed with the County's geotechnical consultant.
Rough Order Schedule
Prep and Excavation of slide area - 8.7.18 to 8.24.18
Installation of SWPP and hydro-seeding - 8.22.18 to 8.31.18
Punch list work 8.30.18 to 9.5.18
Pave and stripe Southside Rd 9.6.18 to 9.7.18 - Open Southside Rd on 9.7.18
Excavate and Pave Blossom Ln 9.10.18 to 9.12.18
Rough Order Cost
Prep and Excavation of slide area: $155,500.00
Installation of SWPP and hydro-seeding: $61,550.00
Punch list work: $17,500.00
Pave and stripe Southside Rd: $46,000.00
Excavate and Pave Blossom Ln: $80,775.00
Total Estimated Remaining Cost: $361,325.00
A 10% contingency has been added to this rough cost estimate to make the contract amount $397,458.00.
BUDGETED: