SUBJECT:

RESOURCE MANAGEMENT AGENCY - J. GUERTIN

Approve contract amendment with Quincy Engineering, extending engineering services regarding the Limekiln Road Bridge replacement project, from June 30, 2018 to June 30, 2019.

SBC FILE NUMBER: 105



AGENDA SECTION:

CONSENT AGENDA

BACKGROUND/SUMMARY:

On June 19, 2012, the County entered into a contract with Quincy Engineers to provide engineering services for the Limekiln Road Bridge replacement project at a cost of $356,116.93.

 

On June 14, 2016, the original contract was amended to add $30,200.00 for additional environmental studies and project design in relation to the bridge replacement project.

 

The project is ongoing, therefore a second amendment is necessary to extend the length of the contract. It is anticipated the bridge replacement will be completed in FY 2018-19.  It is not anticipated that additional funding will be necessary.  Therefore, this amendment will not impact the General Fund.



BUDGETED:

Yes

SBC BUDGET LINE ITEM NUMBER:



CURRENT FY COST:



STAFF RECOMMENDATION:

Approve contract amendment with Quincy Engineering, extending engineering services regarding the Limekiln Road Bridge replacement project, from June 30, 2018 to June 30, 2019, and authorize the Board Chair to sign it.

ADDITIONAL PERSONNEL:
No


BOARD ACTION RESULTS:

Approved per staff recommendation. (5/0 vote)
ATTACHMENTS:
DescriptionUpload DateType
Contract Amendment6/4/2018Contract Amendment