MEETING DATE: 4/3/2018
DEPARTMENT: RESOURCE MANAGEMENT AGENCY
DEPT HEAD/DIRECTOR: John Guertin
AGENDA ITEM PREPARER: Adam Goldstone
SBC DEPT FILE NUMBER: 120.5
SUBJECT:
RESOURCE MANAGEMENT AGENCY - J. GUERTIN
Approve contract with PG&E for utility construction services for the Jail Expansion project in the amount of $21,215.56.
SBC FILE NUMBER: 120.5
AGENDA SECTION:
CONSENT AGENDA
BACKGROUND/SUMMARY:
As part of the necessary work for the Jail Expansion Project, PG&E's gas and electric utility service needs to be upgraded. They have completed their design and will install the new infrastructure. The cost for this work is $21,215.56 and includes a new upsized transformer and additional gas meter. This work was anticipated and was included in the project's budget.
BUDGETED:
Yes