| | | | | | | | Item Number: 31.
MEETING DATE: 6/14/2016
DEPARTMENT: RESOURCE MANAGEMENT AGENCY
DEPT HEAD/DIRECTOR: Brent Barnes
AGENDA ITEM PREPARER: Deems Katada
SBC DEPT FILE NUMBER: 105
SUBJECT:
RESOURCE MANAGEMENT AGENCY - B. BARNES
Approve Contract Amendment #1 with Quincy Engineering for Limekiln Road Bridge Project extending the expiration date to June 30, 2018 and increase the budget by $30,200.00.
SBC FILE NUMBER: 105
AGENDA SECTION:
CONSENT AGENDA
BACKGROUND/SUMMARY:
The contract with Quincy Engineering, Inc., for engineering consulting services and construction support for the Limekiln Road Bridge is set to expire on June 30, 2016. The project has experienced delays due to unanticipated site conditions and required modifications to the original scope of work. A contract amendment is needed to extend the contract timeline for the final design and preparation of plans and specifications. This amendment #1 expands the scope of services to add additional tasks relating to Design, Environmental Technical Reports, and Biological Resources outside of the approved environmental study area, increases the budget by $30,200.00, and extends the term of the contract to June 30, 2018. All other terms and conditions of the original contract remain in place.
BUDGETED:
SBC BUDGET LINE ITEM NUMBER:
CURRENT FY COST:
STAFF RECOMMENDATION:
It is respectfully recommended that the Board of Supervisors:
1. Approve amendment #1 with Quincy Engineering, Inc., for Limekiln Road Bridge Project, for contract term extension from June 30, 2016 to June 30, 2018 and additional scope to $30,200 for a total contract value to $386,316.93; and,
2. Authorize the chair to sign said contract.
ADDITIONAL PERSONNEL:
|
| | | | | | | | BOARD ACTION RESULTS:
This item was pulled for discussion by Supervisor Botelho. Approved per staff recommendation. (4/0 vote, Supervisor De La Cruz absent) | | | |
ATTACHMENTS: | Description | Upload Date | Type | Amended Contract | 6/2/2016 | Contract Amendment |
|
|