Approve Contract with Rincon Consultants, Inc. for Environmental Evaluation under CEQA of the proposed LICO application, a 160-unit residential subdivision for the period of July 28, 2016 through completion in an amount not to exceed $74,121.00.
SBC FILE NUMBER: 790
AGENDA SECTION:
CONSENT AGENDA
BACKGROUND/SUMMARY:
The project applicant is proposing a 160-unit residential subdivision on the approximately 50.7-acre site. The project would require a zone change to Single Family Residential (R-I), which is consistent with the site’s RM designation under the 2035 General Plan.
Access to the project would be provided via two connections to Enterprise Road: one located at the northwest corner of the site and one at the northeast corner of the site. Emergency vehicle access would also be provided in the southeastern corner of the property via connection to Quail Ridge Way. New curb, gutter and landscaping would be installed along the project frontage on Enterprise Road and along both sides of all interior streets. Private sidewalks are proposed on each lot throughout the site. Staff recommends Board of Supervisor contract approval in an amount not to exceed $74,121 with Rincon Consultants, Inc. for the Organization of this information is critical, since it forms the basis for environmental evaluation under CEQA.
BUDGETED:
SBC BUDGET LINE ITEM NUMBER:
CURRENT FY COST:
STAFF RECOMMENDATION:
Staff respectfully recommends Board of Supervisors:
1. Approve Contract with Rincon Consultants, Inc. for the proposed LICO Subdivision Application in an amount not to exceed $74,121, and;
2. Authorize Chair to sign contract.