Item Coversheet

Item Number: 22.



MEETING DATE:  8/8/2016

DEPARTMENT:
RESOURCE MANAGEMENT AGENCY

DEPT HEAD/DIRECTOR: Brent Barnes

AGENDA ITEM PREPARER: Brent Barnes

SBC DEPT FILE NUMBER: 790

SUBJECT:

RESOURCE MANAGEMENT AGENCY - B. BARNES

Approve Amendment #1 to contract with First Carbon Solutions in the amount of $52,800 for Environmental Work related to the Fay Major Subdivision Project for the period of March 3, 2016 to completion; and authorize a 10% change order authority in the amount not to exceed $5,280 to the RMA Director.

SBC FILE NUMBER: 105



AGENDA SECTION:

CONSENT AGENDA

BACKGROUND/SUMMARY:

The Fay Major Subdivision project applicant is proposing to subdivide the project site to create 84 single-family residential lots. Vehicular access would be taken from a single street connection to Southside Road. In March of 2016, your Board approved a contract with First Carbon Solutions to conduct a preliminary environmental review of the project to evaluate the feasibility of using existing environmental documents as the basis for assessing the project. In this case, the County’s General Plan EIR is the applicable CEQA document against which the project will be evaluated. This process is called "tiering". The initial review conducted by First Carbon Solutions concluded that additional project specific review is necessary to meet technical and legal standards.

 

The present contract AMENDMENT would authorize First Carbon Solutions to conduct the required detailed analysis specifically related to the project.



BUDGETED:



SBC BUDGET LINE ITEM NUMBER:



CURRENT FY COST:

0

STAFF RECOMMENDATION:

Staff respectfully recommends that the Board of Supervisors:

1. Approve Amendment #1 to contract with First Carbon Solutions for environmental work associated with the Fay Major Subdivision Project in an amount not to exceed $52,800 and authorize the Chair to sign the contract; and

2. Grant the RMA Director 10% change order authority in an amount not to exceed $5,280.



ADDITIONAL PERSONNEL:
No


BOARD ACTION RESULTS:

Approved per staff recommendation. (4/0 vote, Supervisor Barrios absent)
ATTACHMENTS:
DescriptionUpload DateType
1st Amendment to Contract with Ex. 1 (original contract) attached8/2/2016Contract Amendment