Item Coversheet

Item Number: 20.



MEETING DATE:  8/8/2016

DEPARTMENT:
RESOURCE MANAGEMENT AGENCY

DEPT HEAD/DIRECTOR: Brent Barnes

AGENDA ITEM PREPARER: Adam Goldstone

SBC DEPT FILE NUMBER:

SUBJECT:

RESOURCE MANAGEMENT AGENCY - B. BARNES

Approve contract with In Studio Architecture for architectural services on the Homeless Services Center project in the amount of $66,400.

SBC FILE NUMBER: 105.3



AGENDA SECTION:

CONSENT AGENDA

BACKGROUND/SUMMARY:

Now that the property has been purchased and the project has been approved, full architectural design must occur.  In Studio Architecture was selected through an RFP process last year and has prepared conceptual design and cost estimates to assist us to this point.

BUDGETED:

Yes

SBC BUDGET LINE ITEM NUMBER:



CURRENT FY COST:



STAFF RECOMMENDATION:

1. Approve contract with In Studio Architecture for architectural services for the Homeless Services Center in the amount of $66,400; and

2. Authorize chair to sign the contract



ADDITIONAL PERSONNEL:
No


BOARD ACTION RESULTS:

This item was pulled for discussion by Supervisor Muenzer.  Approved per staff recommendation. (4/0 vote, Supervisor Barrios absent)
ATTACHMENTS:
DescriptionUpload DateType
Contract with Att's A-D7/29/2016Standard Contract