Approve contract with Earth Systems for Geotechnical Investigation Services for the Fire Station #3 Project in the amount of $14,550; and receive Fire Chief update.
SBC FILE NUMBER: 105.3
AGENDA SECTION:
REGULAR AGENDA
BACKGROUND/SUMMARY:
Due to the requirement for the new Fire Station #3 structures to be Essential Services Facilities and the fact that the subject property is located in a FEMA flood zone, a thorough geotechnical investigation is necessary.
BUDGETED:
Yes
SBC BUDGET LINE ITEM NUMBER:
CURRENT FY COST:
STAFF RECOMMENDATION:
1. Approve the contract with Earth Systems for Geotechnical Investigation Services for the Fire Station #3 Project in the amount of $14,550; and
2. Authorize chair to sign the contract.
ADDITIONAL PERSONNEL: No
|